PACRA Upgrades Entity Ratings of Liberty Wind Power 2 Limited

Lahore, March 01, 2023 (PPI-OT): Liberty Mills Limited has set up a 50MW wind power plant “Liberty Wind Power 2 Limited” (LWP2) in Jhimpir, District Thatta, Sindh. LWP2 is awarded a cost plus tariff, with the payments to be received from CPPA-G backed by the sovereign guarantee. The plant successfully achieved its Commercial Operations (COD) on 27th May 2022 and has been supplying electricity to the national grid since then. The Company operates in the regulated power sector. Comfort is drawn from entity’s group association, having strong financial backing. Hydrochina International Engineering Company Limited and Hangzhou Huachen Electric Power Control Company were the EPC contractors for the project and shall also remain its O and M operators for the first two years after COD.

The O and M contractor will be responsible for maintaining the operational benchmarks (Availability: 97%, Capacity: 38%) and shall provide the warranty bond (10% of EPC cost) in the form of irrevocable bank guarantee for 24 months after COD. This will provide additional cushion for the sustainable financial risk profile. Further, the company will maintain the Debt Service Reserve Account (DSRA), which will be backed by 6 months SBLCs, in total providing coverage of six months on its financial obligations till maturity. Foreign and local components of loan have a maturity of 13 and 10 years respectively with quarterly repayments started from Sep, 22.

The project revenues and cash flows remain exposed to wind risk due to seasonal variation in the wind speed which may affect electricity generation, and ultimately cash flows may face seasonality. However, historical wind speeds provide comfort that LWP2 would be able to generate enough cash flows to keep its financial risk manageable. FCFO’s for June’22 stood at PKR 316 million while total receivables were recorded at PKR 403 million, which is mainly representing unbilled billing to the Power Purchaser.

The company has provided 101.976 Gwh of electricity till Jan’23 after achieving COD to national grid. The company is in the process of applying for adjustment / true up in its original tariff and may have to rely on additional financing to service its debt if payments from power purchaser are not recovered on time. However, Power Purchaser has been releasing the due receivable during the month in which respective invoices become due, and the management expects the same trend in future.

The Company has signed Energy Purchase Agreement (“EPA”) with CPPA-G, as per the EPA, in case of non-project missed volumes the power purchaser shall be liable to pay the missed volumes calculated using tariff rates. The Company has adequate insurance coverage. Furthermore, external factors such as any adverse changes in the regulatory framework may impact the ratings. Going forward, the capacity of the Company to generate stable cash flows and timely receipt of payments from the Power purchaser in order to make timely repayments against the project debt remains crucial.

For more information, contact:
Analyst,
The Pakistan Credit Rating Agency Limited (PACRA)
Awami Complex, FB1, Usman Block New Garden Town,
Lahore, Pakistan
Tel: +92-42-5869504-6
Fax: +92-42-5830425
Email: hammad.rashid@pacra.com
Website: www.pacra.com